Jimblebar Iron Ore Project

Project
Proponent: 
BHP Billiton Iron Ore Pty Ltd
Proposal description: 

The proposal is to extend the existing Wheelarra Hill open pits, develop the South Jimblebar and Hashimoto deposits, and to increase the ore processing capacity by 30 million tonnes per annum (mtpa) to 75 mtpa. Open pit mining will occur above and below ground and will involve dewatering. Excess water will be discharged into the Ophthalmia Dam.

Assessment Number: 
1847
Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Iron Ore
Last updated: 
October 22, 2015
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Environmental Protection Statement (EPS)
Extract of determination: 
PDF icon 1847-ChairDets-181010.pdf
Preliminary Environmental Factors: 
Flora and Vegetation
Terrestrial Fauna
Hydrological Processes
Inland Waters Environmental Quality
Date published: 
Monday, 18 October, 2010
4. EPA Report on assessment
EPA Report Number: 
1371
EPA Report: 
PDF icon Jimblebar Iron Ore Project
Key Environmental Factors: 
Flora and Vegetation
Terrestrial Fauna
Hydrological Processes
Inland Waters Environmental Quality
Date published: 
Monday, 18 October, 2010
Appeals close: 
Monday, 1 November, 2010
5. Decision on proposal and implementation of proposal
Ministerial Statement
Comments: 

See related Ministerial Statements 683 and 809.

Date of approval: 
Friday, 18 February, 2011
Ministerial Statement: 
PDF icon Ministerial Statement 857
Post-assessment changes
Section 46 inquiry: 
Jimblebar Iron Ore Project (s46)
s. 45C amendments: 

Attachment 1 to Statement 857 - Increase in land disturbance from 2,042 hectares to 2,300 hectares and increase development envelope from 7,880 hectares to 8,183 hectares. Remove power supply as not a key proposal characteristic - s45C change to proposal approved 22 October 2015.

Attachment 2 to Ministerial Statement 857 - Increase to the Development Envelope from 8,183 ha to 8,324 ha. s45C change to proposal approved 9 November 2018.

Date of approval s. 45C: 
Thursday, 22 October, 2015
Friday, 9 November, 2018