Fremantle Port Inner Harbour and Channel Deepening, Reclamation at Rous Head and Offshore Placement of Dredged Material

Project
Proponent: 
Fremantle Ports
Proposal description: 

Proposal to deepen the Fremantle Inner Harbour, Entrance Channel and the Deep Water Channel, and further reclamation at Rous Head by Fremantle Ports.

Assessment Number: 
1621
Region: 
Perth
Referred under EP Act: 
s38
Industry sector: 
Infrastructure
Last updated: 
March 24, 2011
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Public Environmental Review
Preliminary Environmental Factors: 
Benthic Communities and Habitats
Coastal Processes
Marine Environmental Quality
Date published: 
Monday, 12 December, 2005
3. Assessment
Environmental Review
Public submissions: 
Monday, 19 January, 2009 to Monday, 2 March, 2009
Environmental Review documentation: 
PDF icon Fremantle Port Inner Harbour PER
Proponent response to submissions: 
PDF icon Fremantle Port Inner Harbour - PER supplement and Response to Submissions
4. EPA Report on assessment
EPA Report Number: 
1330
EPA Report: 
PDF icon EPA Report 1330 Fremantle Port Inner Harbour and Channel Dredging
Key Environmental Factors: 
Benthic Communities and Habitats
Coastal Processes
Marine Environmental Quality
Marine Fauna
Date published: 
Monday, 15 June, 2009
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Tuesday, 18 August, 2009
Ministerial Statement: 
PDF icon Ministerial Statement 0801
Post-assessment changes
s. 45C amendments: 

Attachment 1 to Statement 801 – A change to the location of offshore placement of dredged material from Fremantle Ports Inner Harbour and Channel Deepening, and related works – change to proposal approved under s45C on 6 August 2010.

Attachment 2 to Statement 801 – Extension of dredging duration and removal of dredging timeframe indication – change to proposal approved under s45C on 24 March 2011.

Date of approval s. 45C: 
Friday, 6 August, 2010
Thursday, 24 March, 2011