Proposal description: 

Channar Mining Pty Ltd has submitted a proposal to mine iron ore in the Channar Mining Area Hamersley Ranges of Western Australia.

The proposal involves the establishment of primary and secondary crushers adjacent to the mine site to crush the ore. The crushed ore will then be transported by conveyor to Paraburdoo for further treatment. The initial output will be 3 million tonnes per annum (Mt/a) increasing to 10 Mt/a by the ninth year. The expected lifetime of the mine is 22 years and the total tonnage of saleable ore is 200 million tonnes.

Region: 
Pilbara
Referred under EP Act: 
s38
Industry sector: 
Iron Ore
Last updated: 
October 12, 2011
Current Status: 
Ministerial Statement published
Ministerial Statement published
2. Decision on whether to assess this proposal
Chair's Determination: 
Assess - Public Environmental Review
Date published: 
Friday, 20 February, 1987
3. Assessment
Environmental Review
Public submissions: 
Saturday, 10 October, 1987 to Monday, 23 November, 1987
Environmental Review documentation: 
PDF icon PER document
4. EPA Report on assessment
EPA Report Number: 
310
Proponent documents: 
PDF icon Joint venture development of the Channar Mining area
Key Environmental Factors: 
Flora and Vegetation
Terrestrial Fauna
Hydrological Processes
Date published: 
Tuesday, 1 December, 1987
5. Decision on proposal and implementation of proposal
Ministerial Statement
Date of approval: 
Wednesday, 10 February, 1988
Ministerial Statement: 
PDF icon Ministerial Statement 16
Post-assessment changes
s. 45C amendments: 

Attachment 1 to Statement 16 – Change to Schedule 1, Key Characteristics Table – change to proposal approved under s45C on 30 May 2005.

Attachment 2 to Statement 16 – Change to 1988 conceptual layout of mine site to current layout – change to proposal approved under s45C on 15 November 2005.

Attachment 3 to Statement 16 – Amendment to disturbance boundaries – change to proposal approved under s45C on 12 October 2011.

Date of approval s. 45C: 
Monday, 30 May, 2005
Tuesday, 15 November, 2005
Wednesday, 12 October, 2011