Home > Printer-friendly > Printer-friendly > 0805 - Karara Iron Ore Project 215 kilometres east-southeast of Geraldton and 320 kms north-northeast of Perth, Shire of Perenjori

0805 - Karara Iron Ore Project 215 kilometres east-southeast of Geraldton and 320 kms north-northeast of Perth, Shire of Perenjori

Information: 

Attachment 1 to Statement 805 - Relocation of the accommodation village, relocation of the airstrip, consolidation of mine infrastructure and removal of internal roads, a borrow pit and a water pipeline - change to proposal approved under s45C on 15 March 2010.

Attachment 2 to Statement 805 – Increase in disturbance area to allow for increased waste dump area, rail loop and airstrip clearing – change to proposal approved under section 45C on 21 June 2012.

Attachment 3 to Statement 805 – Additional clearing for construction of processing plant to facilitate the phased KIOP Expansion Project – change to proposal approved under section 45C on 20 February 2013.

Attachment 4 to Statement 805 – Dry stack and wet tailings cells within the final tailings storage facility landform, being a single dry stack tailings storage facility - change to proposal approved under section 45C on 13 December 2017.

Attachment 5 to Statement 805 – Increase the current authorised area of disturbance by an additional 69 ha to facilitate:

  • relocation of the landfill facility;
  • extension of the ROM pad;
  • adding additional topsoil storage; and
  • supporting service/infrastructure corridors. 

Change to proposal approved under section 45C on 18 March 2019.

Ministerial Statement File: 
PDF icon Ministerial Statement 805.pdf
Date of approval: 
September 8, 2009
Go to the full case view of this Proposal: 
Karara Iron Ore Project

Source URL:https://www.epa.wa.gov.au/0805-karara-iron-ore-project-215-kilometres-east-southeast-geraldton-and-320-kms-north-northeast