This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: March 8, 1994
The former Gasworks site at East Perth was used for the production of gas from coal between 1922 and 1971. Since decommissioning of the gas plant in 1971, structures have been progressively demolished. The site is now used as a services depot by the State Energy Commission of Western Australia, which is the owner of the site. As a result of past operations, extensive contamination by coal tars, including known carcinogenic and toxic organic chemicals, exists on the site and in adjacent areas of... Read more...Last updated: June 25, 1992
The State Energy Commission have agreed to a request by the Department of Planning and Urban Development to change the proposed route of the Harvey - Kvvinana 330kV transmission line at Mandogalup (near Kwinana). The proposed realignment requires amendments to the environmental conditions of Ministerial Statement 41 , and this is the inquiry under s46 into the proposed amendments. Read more...Last updated: April 30, 1990
The proposal is to construct a power transmission line, with an associated corridor, between the existing Northern Terminal substation and a gas turbine power station at Pinjar which is presently under construction. Read more...Last updated: March 14, 1989
The State Energy Commission is proposing to establish a gas turbine power station at Pinjar, north east of Wanneroo. At the completion of the construction in 1994, the station will comprise eight 35 MW gas turbine units. Read more...Last updated: October 14, 1988
The proposal is for a 330 kV transmission line from Harvey to Kwinana, a distance of approximately 102 km. The first 51 km of the route parallels the existing Bunbury - Cannington 132 kV line from the Harvey Substation site almost to Pinjarra. There are a number of deviations to avoid major road intersections, dwellings and their environs and Pinjarra townsite. Following this , the route joins the existing Muja - Southern Terminal 330 kV line and follows it for most of the next 44 km. There is... Read more...