This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: August 29, 2022
The proposal is for the development of residential, commercial and public open space land uses, a single entrance marina and the management of conservation areas on Lot 5000 and Part Lot 5001 Pipidinny Road and Part Lot 9005 Marmion Ave, Eglinton. The EPA's report on the assessment was published as Bulletin 500, and Ministerial Statement 150 was published on 8 July 1991. In March 2013, Eglinton Estates Pty Ltd wrote to the EPA requesting minor amendments to the existing Implementation... Read more...Last updated: August 4, 2022
Yara Pilbara Fertilisers Pty Ltd propose to modify the existing Pilbara Fertiliser project to include the development of a Renewable Hydrogen Plant and associated infrastructure. The proposal is located approximately 11 km north-west of Karratha in the Pilbara region of Western Australia. The proposal is adjacent to the National Heritage listed area and the Murujuga National Park. The proposal would include a total disturbance of 24.78 hectares. The proposal will result in reduction of... Read more...Last updated: July 21, 2022
Change to condition 3 – Time Limit for Proposal Implementation. Extension of time limit of five years to 18 November 2025. Read more...Last updated: July 1, 2022
The proposal is to construct and operate an iron ore export facility at Balla Balla midway between Port Hedland and Karratha, northwest of Whim Creek in the Pilbara region of WA. Read more...Last updated: June 14, 2022
The Proposal would include the following activities: shore crossing site preparation including installation of temporary facilities along the shoreline at the Pluto LNG Facility to facilitate the installation of the trunkline in shallower depths preparation works associated with the installation of the trunkline including dredging and associated spoil disposal at existing spoil grounds trunkline installation (about 32.7 kilometres long within State waters) shore crossing site reinstatement rock... Read more...Last updated: June 14, 2022
APA Northern Goldfields Interconnect Pty Ltd proposes to construct and operate the Northern Goldfields Interconnect Pipeline. The 300 mm diameter buried gas pipeline will extend for approximately 580 km, starting from Ambania (50 km east of Geraldton) to 40 km south of Leinster where it will connect into the existing Goldfields Gas Pipeline. The project will connect existing gas assets in the Mid West region with existing gas assets in the Northern Goldfields region. The proposal includes... Read more...Last updated: May 25, 2022
Harvey Water propose to construct and operate a pipeline and ocean outfall to dispose brine wastewater. The pipeline will be located between the Kemerton Strategic Industrial Area and the Indian Ocean south of Binningup in the Shire of Harvey. The pipeline will convey brine to a single outlet diffuser outfall. The outfall will be located approximately 400 m from the shoreline and will be installed under the seabed by horizontal directional drilling from the coast. The outlet pipe will protrude... Read more...Last updated: May 18, 2022
The proposal is to excavate and process gypsum ore and overburden from mining lease 70/1161. Inquiry under s46 to change the conditions of Ministerial Statement 730. Read more...Last updated: March 15, 2022
The requested change relates to changing condition 9 in order to contemporise the condition with the Environmental Factor Guideline – Greenhouse Gas (GHG) Emissions (EPA 2020) Read more...Last updated: March 14, 2022
The Public Transport Authority (PTA) proposes to construct and operate a new 13 kilometre (km) dual railway track between Malaga and Ellenbrook. The proposed Malaga to Ellenbrook extends from the proposed Bayswater to Malaga railway line. The proposal includes three new stations at Malaga, Whiteman Park and Ellenbrook with intermodal rail, bus, carpark and active mode (cycling and walking) facilities at each station. A potential future station is also proposed at Bennett Springs and rail... Read more...Last updated: February 2, 2022
Conditions 6-12, 9-1 to 9-5 inclusive, and 12-1 to 12-8 inclusive of Ministerial Statement 873 are to be removed from the statement and conditions 9-1 to 9-5 inclusive and conditions 12-1 to 12-8 inclusive are to be transferred into a new ministerial statement. The change will facilitate the transfer of conditions relevant to the operation of port facilities from Chevron Australia Pty Ltd to the Pilbara Ports Authority via this new Ministerial Statement. Read more...Last updated: February 2, 2022
Change to Condition 9 (Rehabilitation) to remove reference to northern portion of Lot 2 Read more...Last updated: February 2, 2022
The requested changes relate to condition 3 of Statement 1041 (as relevant to Statement 826) for an extension to the Time Limit of Authorisation for Proposal Implementation. Read more...Last updated: February 1, 2022
Changes to condition 7 to remove reference to the onsite brickmaking facility. Read more...Last updated: February 1, 2022
Lynas Kalgoorlie Pty Ltd (Lynas) propose to construct and operate a new Rare Earths Processing Facility at Lot 500 Great Eastern Highway, Yilkari and a By-product storage facility on Common Reserve 8767, Yarri Road, Parkerston in the City of Kalgoorlie-Boulder. The Rare Earths Processing Facility will process rare earth concentrate from the Mt Weld mine to produce a rare earth carbonate for export. Read more...Last updated: January 31, 2022
To build and operate a waste to energy plant on Lot 9500 Leath Road, Kwinana in the Kwinana Industrial Area. Read more...Last updated: January 31, 2022
APH Contractors proposes to extract approximately 2.2 million bank cubic metres of sand from 22.87 hectares over a period of 20 years at an annual extraction rate of 100,000 – 120,000 tonnes per year. Sand will be extracted to a maximum depth of 20m Australian Height Datum (AHD). It is proposed that sand extraction will continue from east of Gelorup Hill and move progressively southwards in 18 sand extraction blocks, each between one and two hectares. Embankments will be restored to 1:4 (14o)... Read more...Last updated: January 25, 2022
Dredging of approximately 3,900,000 cubic metres of material for two new berth pockets and extensions to the existing departure channel and swing basin at Harriet Point and Stanley Point; disposal of dredged material at dredged material management areas. Read more...Last updated: December 24, 2021
The Proponent, FMG Iron Bridge Ltd, proposes to construct and operate the North Star Magnetite Iron Ore Mine, located approximately 110km south of Port Hedland, WA. The Project also includes a borefield in the Canning Basin and a slurry pipeline to transport the ore product to Port Hedland for export. Read more...