This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: January 22, 2013
Establishment of an Industrial Park at Meenaar 18 km east of Northam - Inquiry under s46 of the, Environmental Protection Act 1986, to remove the entire implementation conditions and proponent commitments of Ministerial Statement 293. Read more...Last updated: January 22, 2013
The proposal is for the construction of a deepwater port. Inquiry under s46 regarding changing condition 9 of Ministerial Statement 469 . Read more...Last updated: December 4, 2012
The proposal is for mining of iron ore below the watertable from the Orebody 23 deposit on the Ophthalmia Range, including de-watering operations, approximately 13 kilometres north-east of Newman, Shire of East Pilbara. Read more...Last updated: February 28, 2012
The proposal is to construct and operate the Outer Harbour Development which includes landside and marine infrastructure for the handling and export of iron ore from BHPBIO’s operations. The Boodarie stockyard infrastructure will supply an overland conveyor to a transfer pad located to the west of the existing Finucane Island facilities. A piled jetty will transfer ore material to the ship loaders located at the piled wharf. Read more...Last updated: November 24, 2011
The proposal is for the construction and operation of a mineral sands mine at Gwindinup, approximately 25 kilometres south-south-east of Bunbury and between two and ten kilometres south of the town of Boyanup. Read more...Last updated: November 22, 2011
The proposal involves the construction and operation of an open pit magnetite mine located approximately 90 kilometres east-north-east of Albany, and pipelines for ore slurry transport and return water, connecting the mine site and new port loading facilities in the Port of Albany. Read more...Last updated: March 14, 2011
The proposal is to construct and operate iron ore handling and storage facilities and ancillary infrastructure required to develop and operate a 45 million tonne per annum iron ore export facility at Oakajee, 24km north of Geraldton. Read more...Last updated: March 11, 2011
The proposal is to mine hematite and magnetite iron ore from the Blue Hills North and Terapod deposits, and construction of associated mine infrastructure, upgraded access road to Morawa, Tilley Siding, and powerline corridor in the Midwest region of Western Australia. Read more...Last updated: February 23, 2011
The proposal is to develop an open-cut lead carbonate mine and processing facilities approximately 30 kilometres west of the Wiluna townsite to produce a lead concentrate. The lead concentrates will be refined at the Wiluna minesite to produce lead metal, or alternatively will be transported by road to the Geraldton Port and exported. Post-assessment changes to the proposal stipulate that the lead carbonate concentrate produced at the mine-site is transported in sealed bags within locked... Read more...Last updated: January 20, 2011
The proposal is for the construction and operation of two nominal 229 Megawatt (208 Megawatt net sent-out) subcritical coal-fired base-load generation plants (i.e. Bluewaters Power Station Phases III and IV) on a site adjacent to the existing Bluewaters Phase I and Phase II generating plants located approximately 4.5 kilometres north-east of Collie. The proposal also involves the construction and operation of an approximately 63 kilometre long wastewater discharge pipeline following the same... Read more...Last updated: November 4, 2010
Identification of potential corridors and areas for future installation of water and waste water pipelines and associated infrastructure throughout the southern suburbs of Perth. Read more...Last updated: September 17, 2010
The proposal is to construct and operate the Coolimba Power Station on a site located approximately 15 kilometres (km) south-south-west of Eneabba, and to establish an approximately 20 km long and 100 metre (m) wide infrastructure corridor that will accommodate the construction and operation of: a natural gas pipeline lateral to connect the power station to either the Dampier to Bunbury Natural Gas Pipeline (DBNGP) or the Parmelia Gas Pipeline; and a 330 kV electricity transmission line to... Read more...Last updated: December 1, 2009
The proposal is to construct a deepwater port to service fully loaded Panamax sized vessels (65 000 DWT) at Oakajee, approximately 23 kilometres north of Geraldton. Three site locations (north, south and central) and two different design options (inshore and off-shore) were considered in developing the proposal. The design option favoured by the proponent is an in-shore port design at the northern sector. The port study area is approximately 23 kilometres north of Geraldton. The port will... Read more...Last updated: March 13, 2009
The proposal involves the construction and operation of a 40 Megawatt power plant fuelled by up to 380,000 tonnes (+/-10%) per annum of, Eucalyptus globulus, (Bluegum) and pine plantation wastes, a pipeline for water supply, and a power line connecting the power plant to the sub-station. Read more...Last updated: February 12, 2009
The proposal is to develop an iron ore (haematite) mine at Jack Hills approximately 100 km west of Meekatharra. The project will have a lifespan of approximately seven years (five years of mining, two years of closure activities) and will be a contract mining operation. The project will consist of an open cut mine with one pit up to 140 metres deep (approximately 41.2 MT of ore and waste rock). The floor of the pit will be above the watertable and the pit will not be backfilled. Product will be... Read more...Last updated: March 20, 2008
The proposal is to establish materials stockpiling and handling facilities with a capacity of approximately 4 million tonnes at Cape Preston, approximately 60km west-south-west of Dampier. Read more...Last updated: July 12, 2007
The proposal is for the construction and operation of an ethanol bio-refinery on a 19 hectare site in the Kwinana Industrial Area. Read more...Last updated: October 31, 2006
The proposal involves the construction and operation of an approximately 2.8 million tonnes per annum mineral sands mine and concentrator plant on part Swan Location 128, 354 & 508, Lot 2; part Swan Location 128 & 340, Lot 3; part Swan Location 128, 354, 355, 506, Lot 9; Swan Location 506; portion of each of Swan Locations 354 & 508, Lot 1 and part Swan Location 511 & 536, Lot 7, near the intersection of Brand Highway and Dewar Road, approximately 2.5 kilometres north-west of... Read more...Last updated: June 30, 2006
The proposal is to develop a mineral sand mine one kilometre north of the township of Waroona, which is approximately 140 km south of Perth. The area for assessment has been identified as Mining Tenements M70/735, M70/797 and M70/1089. Read more...Last updated: December 5, 2005
The proposal is to expand Hamersley Iron's iron ore operations at Dampier Port from 95 million tonnes per annum (Mtpa) to 120 Mtpa. The Hamersley Iron Dampier Port operations include rail and port facilities, rail maintenance workshops, a 120MW power station, laboratories and other service and administrative functions. The port operations are located at two terminals – Parker Point (PP) and East Intercourse Island (EII). The proposal is to increase the capacity of the Parker Point terminal... Read more...