This "Search Proposal" function provides all assessment documentation associated with a specific proposal, from referral through to Ministerial Statement, where relevant. Information on a specific proposal not available through this search function can be obtained by contacting DWER, EPA services: info.epa@dwer.wa.gov.au
Visit Environment Online Portal if you cannot locate a specific proposal here.
Last updated: November 25, 2024
The construction of facilities for the development of the Greater Gorgon Gas Fields on the North-West Shelf, and the processing and export of the gas at a liquefied natural gas plant to be constructed on Barrow Island. Read more...Last updated: July 31, 2023
The proposal is to construct and operate port infrastructure which includes a stockyard facility, rail loop, conveyor, wharf and ship-loading facility at Port Hedland. Inquiry under s46 in response to a request to change condition 3 - Time Limit for Proposal Implementation of Ministerial Statement 891 . This proposal has been superseded by the Roy Hill Port Expansion Project . Read more...Last updated: July 31, 2023
The proposal is to construct and operate port infrastructure which includes a stockyard facility, rail loop, conveyor, wharf and ship-loading facility at Port Hedland. This proposal has been superseded by the Roy Hill Port Expansion Project . Read more...Last updated: July 31, 2023
The proposal is to construct and operate port infrastructure which includes a stockyard facility, rail loop, conveyor, wharf and ship-loading facility at Port Hedland. Inquiry under s46 regarding amending the conditions of Ministerial Statement 858 . This proposal has been superseded by the Roy Hill Port Expansion Project . Read more...Last updated: August 12, 2020
The proposal is for dredging of not more than 3,500,000 cubic metres off Anderson Point, for a third ship berth; disposal of dredge spoil on preexisting and previously approved land at Anderson Point; and extension of the approved open-pile wharf. Read more...Last updated: January 17, 2012
The proposal is to construct a sub sea pipeline, onshore gas treatment and compression plant, and sales gas pipeline. The subsea pipeline from the Macedon Gas Field (100 kilometres west of Onslow) connects to the onshore gas treatment and compression plant at Ashburton North (15 kilometres southwest of Onslow). The sales gas pipeline connects the onshore facility to the Dampier to Bunbury Natural Gas (DBNG) Pipeline. Read more...Last updated: December 20, 2002
The proposal is for construction and operation of a methanol plant of 1.05 million tonnes per annum (Mt/a) nominal capacity, at Withnell East industrial area on the Burrup Peninsula The proposal includes the installation of a gas supply pipeline, product pipeline, seawater supply pipeline and wastewater discharge pipeline to be situated in infrastructure corridors for which the Department of Mineral and Petroleum Resources (MPR) will be proponent. The plant footprint will occupy approximately... Read more...Last updated: April 10, 2002
The proposal involves an expansion of the existing Dampier Public Wharf to provide improved facilities capable of servicing the future needs of industry in the area. The key components of the proposal are: construction of a 60-81 m long load-out facility south of the existing wharf; cut and fill operations to create a land backing to the facility (1.9 ha, of which 0.8 ha is reclaimed land); and quarrying of a 4.1 ha cargo lay-down and storage area. Read more...Last updated: February 11, 2000
Woodside Energy Limited proposes to construct and operate additional Liquefied Natural Gas (LNG) processing trains, the current proposal being for two trains with a total additional capacity of 8 Mtpa at its onshore gas plant on the Burrup. Read more...Last updated: June 19, 1997
The proposal is to carry out a program of appraisal drilling on the Wonnich petroleum field within permit area TP/8. Read more...