Last updated: July 21, 2022
Change to condition 3 – Time Limit for Proposal Implementation. Extension of time limit of five years to 18 November 2025. Read more...Last updated: July 1, 2022
The proposal is to construct and operate an iron ore export facility at Balla Balla midway between Port Hedland and Karratha, northwest of Whim Creek in the Pilbara region of WA. Read more...Last updated: June 14, 2022
The Proposal would include the following activities: shore crossing site preparation including installation of temporary facilities along the shoreline at the Pluto LNG Facility to facilitate the installation of the trunkline in shallower depths preparation works associated with the installation of the trunkline including dredging and associated spoil disposal at existing spoil grounds trunkline installation (about 32.7 kilometres long within State waters) shore crossing site reinstatement rock... Read more...Last updated: May 25, 2022
Harvey Water propose to construct and operate a pipeline and ocean outfall to dispose brine wastewater. The pipeline will be located between the Kemerton Strategic Industrial Area and the Indian Ocean south of Binningup in the Shire of Harvey. The pipeline will convey brine to a single outlet diffuser outfall. The outfall will be located approximately 400 m from the shoreline and will be installed under the seabed by horizontal directional drilling from the coast. The outlet pipe will protrude... Read more...Last updated: February 2, 2022
The requested changes relate to condition 3 of Statement 1041 (as relevant to Statement 826) for an extension to the Time Limit of Authorisation for Proposal Implementation. Read more...Last updated: February 2, 2022
Conditions 6-12, 9-1 to 9-5 inclusive, and 12-1 to 12-8 inclusive of Ministerial Statement 873 are to be removed from the statement and conditions 9-1 to 9-5 inclusive and conditions 12-1 to 12-8 inclusive are to be transferred into a new ministerial statement. The change will facilitate the transfer of conditions relevant to the operation of port facilities from Chevron Australia Pty Ltd to the Pilbara Ports Authority via this new Ministerial Statement. Read more...Last updated: January 25, 2022
Dredging of approximately 3,900,000 cubic metres of material for two new berth pockets and extensions to the existing departure channel and swing basin at Harriet Point and Stanley Point; disposal of dredged material at dredged material management areas. Read more...