Summary: The proposal involves the dredging of not more than 14.2 million cubic metres (Mm3) of material for eight new berth pockets, a turning circle and a link to the existing shipping channel. The proposal also involves the construction of two new land based dredge management areas (DMMAs). Dredged material will be disposed offshore at an existing disposal ground in Commonwealth waters and the new and existing DMMAs, as documented in schedule 1 of this statement.
Attachment 1 to Statement 859 – Relocation of DMMA G Discharge Point and Modification of Zone of Permanent Mangrove loss - change to proposal approved under s45C on 27 October 2011.
Attachment 2 to Statement 859 – Realignment of the access track between Utah Point Road and the dredging area, and associated changes to the zone of permanent mangrove loss – change to proposal approved under s45C on 2 May 2012.
Release Date: 15 March 2011
Status: Final
Click here to view the document (file type: Acrobat PDF file size: 5.24 MB)
Appeals close